 Photo
showing the dismantled terracotta windows at the east end of Pool 2 - 26th July
2005
 Five
weeks later - Photo showing the rebuilt terracotta windows at the east end of
Pool 2 - 31st August 2005
 The
red arrows above show the new terracotta blocks that have been made for the terracotta
windows at the east end of Pool 2.
 The
filter for Pool 2 as of 9th August
 The
filter for Pool 2 as of 31st August. We have welded on two access covers so that
removal of the sand is far easier in future
 Photo
of the worker inside the filter for Pool 2
 Close
of the laterals inside Pool 2 Filter. These are at the bottom of the tank, through
which the water enters. You can see how the sand beneath these laterals has formed
into solid rock
 Inside
Pool 2 Filter after it was shot blasted
 Inside
Pool 2 Filter after it was coated in Glass Reinforced Plastic
| Moseley
Road baths is still on target to re-open in early October. It is most likely to
be Sunday 9th October 2005. The staff want to re-open it on a Sunday since it
will only be a half day and they will be able to iron out any unforeseen problems,
when the pool shuts in the evening. Chimney The
Boiler House Chimney work is 98% complete. It had been dismantled brick-by-brick
to 10metres below its original height. It is being rebuilt with stainless steel
tube inside it. The
cast iron cap will be delivered back to site during week starting 5th Sept. The
9th Sept has been pencilled in as to when it will be hoisted back into place.
Pool 2 The
terracotta windows at each of the pool have been careful dismantled and new terracotta
blocks made to replace crumbling blocks. The
terracotta window and glass at the shallow end will be complete by 31st August.
The scaffolding will be removed by the 2nd Sept. The
terracotta window and glass at the deep end will be complete by 8th Sept. The
scaffolding will be removed a few days later. Glass
will be put in the terracotta windows to replace the Perspex that has been in
them for over 30 years. The
original stain glass will be put back in at the top of each terracotta window
at both ends of the pool. The bottom ¾ of each window will be toughened
rippled glass. I had previously stated that the entire window at the shallow end
would be stained glass. Apparently, the stain glass still existed in the top sections
of each set of windows. The glass has been taken out and re-set in new leaded
canes. After the
scaffolding has been taken out, all the electrical lights will be checked for
safety and modified/repaired if required. This should take a few days. We
have then set aside two weeks for swimming pool staff to carefully clean the pool
(removing any shape objects in the grouting between the tiles) and re-fill it.
Re-filling takes one week. The
boilers for Pool 2 have been tested at full power and are operating fine. They
haven't operated at full power for over 12 months Terracotta
Domes The domes have been re-pointed and the new steel structure inserted
inside each dome. This will replace the rusted steel structure which caused many
of the terracotta blocks to move.
Roof Work
is on going to repair as many leaks and missing gutterings/slates as possible.
Pool 2 suffered
terribly from roof leaks prior to its closure in 2004. Out of it 34 cubicles,
10 would have to be closed whenever it rained. We hope to reduce this number significantly. Swimming
Pool Filter The large filter for Pool 2 is in the process of now been refilled
with Leighton Buzzard sand. Over a tonne of sand (plus debri from the pool) was
removed by hand. It appears that this filter had not been emptied for decades,
since the sand had congealed into solid rock at the bottom of the filter tank. The
filter has had its numerous leaks welded up and the interior coated with glass
reinforced plastic. Future
Restoration of Moseley Road Swimming Baths A bid has been put into the
Council for £200,000 to do a Conservation Survey of the building - this
is needed for any HLF bid. We will know on the 12th September if we have been
successful |